TRAINING COURSE AND INSTALLATION OF A WIND TURBINE 200 |
| These training
activities were done for teachers of a training center for industrial
workers, SENATI. The first part of the course was theoretical and subjects as wind potential measurement, wind energy applications and issues related with wind turbines design were treated. The second part included, as part of the activities of the course, an installation of a Wind Turbine 200 unit. This installation was done at SENATI Villa El Salvador. Some views of the activities during the course: |
|
|
|
Assembly of blades to the Permanent Magnet Generator |
|
|
|
Assembling the permanent magnet generator. |
|
|
|
Electrical connection of the wind turbine to the conductor that goes down through the pipe tower to the rectifier |
|
|
|
Final adjustments before erection |
|
|
|
Erection of wind turbine |
|
|
|
Wind Turbine 200 installed |
|
|
|
Working on the electronic control. Inside the box, the rectifier is at left and the electronic control is at right. |
|
© 2011 DENERTEC S.A.C. All rights reserved |